According to the PMBOK (7th edition) by the Project Management Institute (PMI), Fixed Price Incentive Fee Contract (FPIF) is a "type of contract where the buyer pays the seller a set amount (as defined by the contract), and the seller can earn an additional amount if the seller meets the defined performance criteria".
One applies to fixed-price contracts, another to cost reimbursement contracts, and the third to time and materials or labor hours. [5] All three of these clauses give the government the right, at any time and without notice to the sureties, to make changes in the work within the general scope of the contract. The clause for fixed-price ...
A fixed-price contract is a contract where the contract payment does not depend on the amount of resources or time expended by the contractor, as opposed to cost-plus contracts. Fixed-price contracts are often used for military and government contractors to put the risk on the side of the vendor and control costs.
Calculation of Point of Total assumption (the case when EAC exceeds PTA that should be treated as a risk trigger, is shown) The point of total assumption (PTA) is a point on the cost line of the profit-cost curve determined by the contract elements associated with a fixed price plus incentive-Firm Target (FPI) contract above which the seller effectively bears all the costs of a cost overrun.
Cost plus a fixed-fee (CPFF) contracts pay costs plus a pre-determined fee that was agreed upon at the time of contract formation. Cost-plus-incentive fee ( CPIF ) contracts have a larger fee awarded for contracts which meet or exceed certain performance goals, for example being on schedule and any cost savings.
Thus, while credit cards which charge an annual fee plus a per-transaction fee is a good example of a two-part tariff, a fixed fee charged by a car rental company in addition to a per-kilometer fuel fee is not so good, because the fixed fee may reflect fixed costs such as registration and insurance which the firm must recoup in this manner.
Distribution and service fees are fees paid by the fund out of fund assets to cover the costs of marketing and selling fund shares and sometimes to cover the costs of providing shareholder services. They are also called 12b-1 fees after section 12 of the Investment Company Act of 1940. "Distribution fees" include fees to compensate brokers and ...
Typical Lump Sum Contract Structure. A lump sum contract in construction is one type of construction contract, sometimes referred to as stipulated-sum, where a single price is quoted for an entire project based on plans and specifications and covers the entire project and the owner knows exactly how much the work will cost in advance. [1]