The PERT distribution has a smoother shape than the triangular distribution. The triangular distribution has a mean equal to the average of the three parameters: = + + which (unlike PERT) places equal emphasis on the extreme values which are usually less-well known than the most likely value, and is therefore less reliable.
This distribution for a = 0, b = 1 and c = 0.5—the mode (i.e., the peak) is exactly in the middle of the interval—corresponds to the distribution of the mean of two standard uniform variables, that is, the distribution of X = (X 1 + X 2) / 2, where X 1, X 2 are two independent random variables with standard uniform distribution in [0, 1]. [1]
The triangular distribution on [a, b], a special case of which is the distribution of the sum of two independent uniformly distributed random variables (the convolution of two uniform distributions). The trapezoidal distribution; The truncated normal distribution on [a, b]. The U-quadratic distribution on [a, b].
PERT network chart for a seven-month project with five milestones (10 through 50) and six activities (A through F). The program evaluation and review technique (PERT) is a statistical tool used in project management, which was designed to analyze and represent the tasks involved in completing a given project.
For example, a triangular distribution might be used, depending on the application. In three-point estimation, three figures are produced initially for every distribution that is required, based on prior experience or best-guesses: a = the best-case estimate; m = the most likely estimate; b = the worst-case estimate
PERT network chart for a seven-month project with five milestones (10 through 50) and six activities (A through F). work breakdown structure, A work breakdown structure (WBS), in project management is a deliverable oriented decomposition of a project into smaller components. A Gantt chart is a type of bar chart, that illustrates a project schedule.
PERT chart for a project with five milestones (10 through 50) and six activities (A through F). The project has two critical paths: activities B and C, or A, D, and F – giving a minimum project time of 7 months with fast tracking. Activity E is sub-critical, and has a float of 1 month.
It's much less popular than PERT (Program Evaluation and Review Technique) or CPM (Critical Path Method) however, it allows some of those methods limitations to be addressed. The main limitations of PERT or CPM that might be addressed by GERT are: there are no alternative paths - all activities have to be performed